WORK

Completion of Feitais Crushing Chamber, Excavation and Concreting of the Silos, Expansion of St.ª Bárbara Gallery and Reinforcement of the Gallery M 180

Designation of the Works

Completion of Feitais Crushing Chamber, Excavation and Concreting of the Silos, Expansion of St.ª Bárbara Gallery and Reinforcement of the Gallery M 180

Works Owner

Pirites Alentejanas, S.A.

Client

Pirites Alentejanas, S.A.

Description

Mining. Construction of infrastructures for new mining areas, including:
Completion Works for the Excavation and Concreting of the Silos.
Expansion and accesses of Sta. Bárbara tunnel which makes the connection between Moinho and Feitais Mines.
Reinforcement of the Gallery M 180.

Location/Site

Aljustrel, Portugal

Start Date

June, 2009

Execution Period

6 months