WORK

Improvement of Tornos Watercourse South Section 2nd Phase

Designation of the Works

Improvement of Tornos Watercourse South Section 2nd Phase

Works Owner

IGA – Investimentos e Gestão da Água, S.A.

Client

IGA – Investimentos e Gestão da Água, S.A.

Description

This Contract Job comprised the construction of a reinforced concrete watercourse about 29,000 metres long, the construction of 4 support houses, the fitting of equipment at the watercourse and the construction of a pontoon and the laying of a gangway in a 2.600 metres long tunnel. Concrete – 7.000 m³. Mesh-Reinforcement – 60.000 m². Pultrusion Gangway – 2.600 m.

Location/Site

Funchal, Machico - R.A. Madeira

Start Date

October, 2010

Execution Period

36 months