WORK

Ponta do Sol Tunnel

Designation of the Works

Link Road to the Town Ponta do Sol / Link Road to the Town Ponta do Sol – Emergency Galleries

Works Owner

Regional Office for Social Equipment and Transportation – Directorate of Regional Roads – A.R. Madeira

Client

Regional Office for Social Equipment and Transportation – Directorate of Regional Roads – A.R. Madeira

Description

Construction of the road tunnel of the Town Ponta do Sol, 2.682 m long and transverse section varying between 75 m2 and 101 m2 / Construction of the emergency galleries of the tunnel of the Town Ponta do Sol , with lengths of 119m and 71 m. Excavation: 210.000 m3. Concrete: 22.000 m3.

Location/Site

Ponta do Sol, R.A. Madeira, Portugal

Start Date

March 2002

Execution Period

25 months