WORK

Tunnel execution of the 52nd. and 53rd. Partial Sections of the Yellow Line

Designation of the Works

Tunnel execution of the 52nd. and 53rd. Partial Sections of the Yellow Line

Works Owner

Metropolitano de Lisboa, E.P.E.

Client

Metropolitano de Lisboa, E.P.E.

Description

Tunnel execution of the 52nd. and 53rd. Partial Sections of the Lisbon Underground Yellow Line. The total underground tunnel length of these two sections is 739 m (357 m and 382 m, respectively). The excavation section is about 70 m2. Excavation: 52.145 m3. Concrete: 9.426 m3

Location/Site

Lisboa, Portugal

Start Date

February, 2001

Execution Period

12 months